Meta Secures 1.6GW AI Capacity From Crusoe

Bloomberg reported that Meta Platforms contracted roughly 1.6 gigawatts (1.6 GW) of AI computing capacity from data center developer Crusoe, spanning two planned campuses in Childress, Texas, and Warrenton, Missouri. Reuters, which carried the Bloomberg report, said neither Meta nor Crusoe immediately responded to requests for comment and that the report could not be independently verified. Bloomberg and subsequent coverage said financial terms and delivery timing were not disclosed. Separate reporting by MLQ and other outlets notes that Crusoe has said its contracted capacity approaches 5 GW with a broader pipeline above 20 GW, which would make a 1.6 GW commitment a material share of Crusoe's contracted base if confirmed. Observers will watch for formal confirmation, timing, and energy supply details.
What happened
Bloomberg reported that Meta Platforms contracted roughly 1.6 gigawatts (1.6 GW) of AI computing capacity from data center developer Crusoe, covering two planned sites in Childress, Texas, and Warrenton, Missouri. DCD (Data Center Dynamics) and Reuters, which carried the Bloomberg account, confirmed that neither Meta nor Crusoe immediately responded to requests for comment and that financial terms and timelines were not disclosed.
Site details
The Childress campus is tied to a 1 GW ERCOT-approved interconnect at a Lancium-linked clean campus site. The Warrenton campus is planned on an approximately 340-acre parcel comprising two 805,000 sq ft data center buildings and a 40,000 sq ft administration building (DCD). Crusoe earlier built the 1.2 GW campus in Abilene, Texas for Oracle/OpenAI and a 900 MW campus at the same site for Microsoft.
Crusoe's pipeline
Per Crusoe's own disclosures reported by DCD, the company's contracted AI infrastructure capacity had reached 4.9 GW, spanning data center projects and its Crusoe Cloud AI platform, with a total development pipeline exceeding 40 GW. The reported 1.6 GW Meta commitment would represent a material share of Crusoe's contracted base if confirmed.
Industry context
Meta has been significantly expanding compute capacity across multiple providers. The company has signed a $27 billion AI infrastructure contract with Nebius, a $21 billion agreement with CoreWeave, and a multi-billion-dollar agreement with AWS for Graviton5 AI chips. Meta CEO Mark Zuckerberg recently signaled the company is exploring a cloud computing offering of its own. A new "Meta Compute" division was established at the start of 2026, with Zuckerberg describing plans to build "tens of gigawatts this decade" (DCD).
What to watch
Observers will look for formal confirmation from Meta or Crusoe, the split of capacity between the two campuses, contract duration and pricing, and the timeline for equipment delivery and commissioning. Energy sourcing, grid interconnect upgrades, and permitting at both sites are additional indicators of when capacity could become operational.
Scoring Rationale
A Bloomberg-sourced major infrastructure deal committing 1.6 GW of AI compute capacity across two U.S. data center campuses, confirmed by DCD with precise site details. The scale is material for AI infrastructure teams and represents a significant portion of Crusoe's contracted pipeline. Scored in the Notable range: a large capacity commitment but not a frontier model release or groundbreaking new technology.