Data Center Developer Sues IID for Colorado River Water

Imperial Valley Computer Manufacturing filed a June 5 lawsuit seeking Colorado River water for its proposed Imperial Valley AI data center. KPBS reports the project wants about 260 million gallons a year after plans to use municipal wastewater fell through. The developer says fallowing nearby farmland would offset the demand; the irrigation district has declined to comment on pending litigation.
Imperial Valley Computer Manufacturing (IVCM) filed a June 5 lawsuit against the Imperial Irrigation District (IID) seeking water service for its proposed AI data center in California's Imperial Valley. The court filing is the originating record; KPBS reports that the request amounts to about 260 million gallons of Colorado River water per year.
The request follows earlier developer statements that the facility would use recycled municipal wastewater rather than river water. KPBS reports that talks with the cities of Imperial and El Centro did not produce those wastewater agreements, after which IVCM applied to IID. The company says IID rejected that application in May. IID declined to discuss the dispute with KPBS and KYMA because the litigation is pending.
The developer's offset argument
KPBS reports that the proposed cooling system would require roughly 750,000 gallons per day. IVCM argues that it has leased about 160 acres of nearby farmland and can fallow that land, then redirect its existing water service to the data center. The company says this would avoid increasing net demand on the Colorado River system.
That is the developer's legal and operational position, not a ruling. The lawsuit remains unresolved, and the retrieved sources do not establish that IID must approve the transfer or that the proposed offset satisfies every applicable water-service rule.
Why the case matters
CalMatters describes the proposed facility as a nearly one-million-square-foot hyperscale project intended for AI and machine-learning workloads. It also reports that Imperial County imposed a 45-day data-center moratorium in June and formed a public commission to advise on zoning policy after local opposition.
The water lawsuit is separate from the developer's challenge to that moratorium, but both disputes expose the same infrastructure dependency: a large compute project cannot proceed on electrical capacity and land approvals alone. Cooling design, a legally secure water source, environmental review and community acceptance can become coupled constraints.
For data-center planners, the practical lesson is narrower than the lawsuit's outcome. Water assumptions should be documented and secured early, including source, volume, transfer rights, drought exposure and fallback cooling design. Here, the move from a wastewater plan to contested river-water access turned a cooling requirement into litigation before the proposed facility began operating.
Key Points
- 1IVCM filed a June 5 lawsuit seeking water service for a proposed AI data center; KPBS puts the request at about 260 million gallons per year.
- 2The developer says fallowing about 160 acres of nearby farmland would offset the project's demand, but that claim has not been adjudicated.
- 3The dispute shows how cooling-water rights, permitting and grid access can become linked constraints for large AI infrastructure projects.
Scoring Rationale
The unresolved case concerns cooling-water access for a proposed hyperscale AI facility in a water-constrained region. It is a useful infrastructure and permitting case, but the immediate impact remains local and the project is not yet operating.
Sources
Primary source and supporting public references used for this report.
View 3 more sources
- Imperial Valley data center developer files lawsuit seeking access to Colorado River waterkpbs.org
- Data center developer sues IID for refusing water service in Imperial Countykyma.com
- This million-square-foot data center would be the biggest in the state. How local leaders are challenging itcalmatters.org
Practice with real Ad Tech data
90 SQL & Python problems · 15 industry datasets
250 free problems · No credit card
See all Ad Tech problems